ERC TO MERALCO: REFUND P1.99B TO CONSUMERS

The Energy Regulatory Commission (ERC) has ordered the Manila Electric Company (MERALCO) to refund P1,987,739,617.40 to its customers, after revaluing MERALCO’s regulatory asset base and disallowing certain pension and employee benefit expenses in compliance with the Supreme Court’s decision in NASECORE v. ERC (G.R. No. 226443).

The Order, issued in ERC Case Nos. 2001-646 and 2001-900 (the MERALCO Unbundling Case), was deliberated and approved by the Commission during its meeting recently.

The refund will be implemented on the next billing cycle from MERALCO’s receipt of the Order, will appear on customers’ bills as a separate line item labeled “RAB Refund”, and will run for a period of three (3) months, or until the full amount has been fully refunded.

For residential and small commercial customers (Residential and General Service A), the refund rate is PO.2611 per kilowatt-hour. A household consuming 200 kWh a month will receive a credit of about P52 per month, or roughly P157 over the three-month refund period.

“This refund could not come at a better time,” ERC Chairperson and CEO Francis Saturnino Juan said. 

“By acting decisively and completing this case now, the Commission ensures that the amount due to consumers is returned when they need it most.”

“MERALCO customers are already feeling the pressure of rising generation charges brought about by higher fuel prices, the depreciation of the peso, and a tight demand-supply margin in the grid. By acting decisively and completing this case now, the Commission ensures that the amount due to consumers is returned when they need it most, and that the refund will help cushion the impact of these increases on their monthly bills,” Juan explained.

“Just as important, this decision fulfills the Supreme Court’s directive. Consumers should pay only for what is necessary to deliver electricity in the least-cost manner, as the EPIRA requires. Assets will be valued on the basis of what they actually cost, and expenses that a utility cannot justify will not be passed on to the public,” he added.

As a background, in its Unbundling Decision of March 20, 2003, as modified by its Order of May 30, 2003 (2003 Unbundling Decision), the ERC set MERALCO’s rates for the period based on a test-year 2000 revenue requirement. 

The value of MERALCO’s utility plant, a key component of its rate base, was determined using an appraisal based on current or replacement cost, resulting in an adjusted total plant value of P69.916 billion.

On October 8, 2019, the Supreme Court, acting on a petition filed by the National Association of Electricity Consumers for Reforms, Inc. (NASECORE), declared void the use of current or replacement cost in valuing MERALCO’s regulatory asset base (RAB).

The Court directed the ERC to (1) determine anew the valuation of MERALCO’s RAB, and (2) set the parameters for deciding whether expenses not directly and entirely related to the operation of a distribution utility may be passed on, wholly or partially, to consumers, to the end that electricity is provided “in the least cost manner”.

The Supreme Court denied the motions for reconsideration of MERALCO, the ERC and the intervenors in a Resolution dated January 14, 2025, which the ERC received on February 25, 2025. The Supreme Court decision thus became final and executory.

To comply with the Supreme Court’s ruling, after public consultations, the ERC adopted Resolution No. 19, Series of 2025, prescribing the Trending Method for valuing MERALCO’s RAB for the period covered by the decision. Under this method, the historical acquisition cost of each utility asset is adjusted using published price indices, preserving the historical cost basis of the assets rather than estimating what it would cost to replace them.

On February 27, 2026, the ERC directed MERALCO to submit a new asset valuation using the Trending Method. MERALCO filed its valuation report on May 4, 2026, placing the trended value of its RAB as of December 31, 2000 at P70.633 billion. 

The ERC then engaged the accounting firm Cafirma, Ong & Co., CPAs to independently review and validate MERALCO’s asset information, historical cost records, depreciation parameters, assumptions and computations. It also required MERALCO to submit additional supporting documents in August 2026.

After the independent validation and its own evaluation, the ERC set MERALCO’s RAB as of December 31, 2000 at P70.595 billion. Applying the disallowances the ERC had imposed in 2003, restated to trended values to keep them consistent with the revalued asset base, the adjusted total plant value comes to P67.782 billion.

This is P2.134 billion lower than the P69.916 billion previously recognized in rates.

Applying the ERC-approved rate of return of 15.50% to this reduction, the Commission found that MERALCO over-recovered P330.8 million a year in return on its plant in service.

The ERC also reviewed MERALCO’s allowed operating expenses for the 2003 Unbundling Decision, including those the Commission on Audit had recommended for disallowance. Among these were MERALCO’s employee pension and other benefits, which were not sufficiently justified as necessary and reasonable costs of providing distribution service in the 2003 Unbundling Decision.

The Supreme Court recognized that pension costs are necessary expenses but held that MERALCO must justify their amounts. MERALCO’s submissions, however, showed only overall totals, without the breakdown of salary scales and benefits needed to establish their reasonableness.

In compliance with the Court’s second directive, the ERC laid down five parameters for deciding whether an expense not directly and entirely related to distribution operations may be charged to consumers:

Necessity: the expense must be necessary, proper or incidental to regulated distribution service.

Reasonableness: the amount must be reasonable compared with statutory, industry or market levels and with levels the ERC previously recognized.

Attribution: where an expense serves both regulated and non-regulated activities, only the documented share attributable to distribution service may be recovered.

Substantiation: the utility bears the burden of proving the expense with competent documents, such as salary scales, benefit plans and actuarial valuations; unsubstantiated expenses are excluded.

Least cost: any doubt is resolved in favor of the least-cost principle under Section 23 of the Electric Power Industry Reform Act (EPIRA).

The ERC disallowed P89.82 million in pension and employee benefit expenses, which may not be passed on to consumers.

Applying these parameters, the ERC disallowed P89.82 million in pension and employee benefit expenses, which may not be passed on to consumers.

Together, the over-recovery on return on plant (P330.8 million) and the disallowed pension and benefit expenses (P89.8 million) amount to an annual over-recovery of P420.6 million. Based on the billing determinant in the 2003 unbundled rates, the equivalent refund rate is at P0.0188 per kWh. Applied to MERALCO’s actual energy sales from April 2003 to June 2007, consumers are entitled to a total refund of P1,987,739,617.40.