MMDA COMPLETES ‘DELAYED’ FLOOD CONTROL PROJECTS

The Metropolitan Manila Development Authority (MMDA) said the flood control projects that the Commission on Audit (COA) cited as delayed in 2021 have been substantially completed this year.

Baltazar Melgar, head of MMDA Flood Control and Sewerage Management Office (FCSMO), said the programmed 59 flood control projects in Metro Manila for 2021 were not completed or left unfinished due to several factors.

“The programmed 59 flood control projects in Metro Manila for 2021 were not completed or left unfinished due to several factors.”

These reasons, according to Melgar, include the following: delayed procurement process due to the COVID-19 pandemic; late or pending issuance of clearances from local government units and other concerned government offices; right-of-way issues; relocation of informal settler families; change in order due to additional items/realignment of activities based on current situation/conditions on-site upon implementation; and restrictions on worker and equipment mobility brought by the pandemic, among others.

According to him, the COA-reported “projects are only minor ones like pipe-laying, drainage and riverbank improvements, and rehabilitation of waterways leading to agency-operated pumping stations”.

“These flood mitigating projects are operational and serviceable this year,” Melgar said.

“We are reassessing and recalibrating our processes to ensure timely completion of our flood control projects.”

“Now that we are slowly returning to normal following measures and restrictions to curb COVID-19, we are reassessing and recalibrating our processes to ensure timely completion of our flood control projects,” he added.

This rainy season, Melgar said, all pumping stations of the agency are working at full capacity, with the necessary power and fuel in place.

The agency operates 77 pumping stations in strategic locations in Metro Manila.

Also, flood-mitigation activities aimed at declogging and cleaning up waterways such as creeks and esteros are conducted all year round with the aim of maximizing the conveyance capacity of open waterways and preventing flooding.

Melgar is currently the officer-in-charge (OIC) of MMDA being its most senior career official.

Home

SHARE THIS ARTICLE

Leave a Reply

Your email address will not be published. Required fields are marked *